Scheduling repetitive construction projects: structured literature review

    Michał Tomczak   Affiliation
    ; Piotr Jaśkowski   Affiliation

Abstract

Construction projects that involve repetitive operations are often referred to as repetitive construction projects. Scheduling them proves a task more demanding than in the case of projects in other industries. Typical objectives of optimization, a characteristic set of constraints, as well as the schedule’s susceptibility to the propagation of disruptions caused by materializing risks, call for specific scheduling methods. The authors review the literature to summarize the existing repetitive scheduling methods and put forward their classification to identify the method’s aspects needing refinement. This is done to point to directions of further research. The authors hope that this study will contribute to better identification of existing problems in planning repetitive construction projects and faster development of decision support systems, eagerly anticipated by the construction practitioners. Though the focus is on applications to construction projects, the repetitive scheduling methods that account for volatile operating conditions may be of interest to researchers who develop planning techniques for other industries.

Keyword : construction project management, construction project planning, construction project scheduling, project management, project schedules, repetitive construction projects

How to Cite
Tomczak, M., & Jaśkowski, P. (2022). Scheduling repetitive construction projects: structured literature review. Journal of Civil Engineering and Management, 28(6), 422–442. https://doi.org/10.3846/jcem.2022.16943
Published in Issue
May 27, 2022
Abstract Views
2286
PDF Downloads
1384
Creative Commons License

This work is licensed under a Creative Commons Attribution 4.0 International License.

References

Abbasnezhad, K., Ansari, R., & Mahdikhani, M. (2020). Schedule risk assessments using a precedence network: An object-oriented Bayesian approach. Iranian Journal of Science and Technology, Transactions of Civil Engineering, 46, 1737–1753. https://doi.org/10.1007/s40996-020-00550-2

Abd El Razek, R. H., Diab, A. M., Hafez, S. M., & Aziz, R. F. (2010). Time-cost-quality trade-off software by using simplified Genetic algorithm for typical-repetitive construction projects. International Journal of Civil and Environmental Engineering, 4(1), 22–31.

Abdallah, M., & Marzouk, M. (2013). Planning of tunneling projects using computer simulation and fuzzy decision making. Journal of Civil Engineering and Management, 19(4), 591–607. https://doi.org/10.3846/13923730.2013.793608

Abdallah, M., & Alshahri, A. (2019). Optimizing planning of build–operate–transfer projects to maximize investor profit. Canadian Journal of Civil Engineering, 46(1), 26–37. https://doi.org/10.1139/cjce-2017-0327

Adeli, H., & Karim, A. (1997). Scheduling/cost optimization and neural dynamics model for construction. Journal of Construction Engineering and Management, 123(4), 450–458. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:4(450)

Agrama, F. A. E. M. (2011). Linear projects scheduling using spreadsheets features. Alexandria Engineering Journal, 50(2), 179–185. https://doi.org/10.1016/j.aej.2011.01.018

Agrama, F. A. E. M. (2014). Multi-objective genetic optimization for scheduling a multi-storey building. Automation in Construction, 44, 119–128. https://doi.org/10.1016/j.autcon.2014.04.005

Ali, M. M., & Elazouni, A. (2009). Finance-based CPM/LOB scheduling of projects with repetitive non-serial activities. Construction Management and Economics, 27(9), 839–856. https://doi.org/10.1080/01446190903191764

Altuwaim, A., & El-Rayes, K. (2018a). Minimizing duration and crew work interruptions of repetitive construction projects. Automation in Construction, 88, 59–72. https://doi.org/10.1016/j.autcon.2017.12.024

Altuwaim, A., & El-Rayes, K. (2018b). Optimizing the scheduling of repetitive construction to minimize interruption cost. Journal of Construction Engineering and Management, 144(7), 04018051. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001510

Ammar, M. A. (2003). Float analysis of non-serial repetitive activities. Construction Management and Economics, 21(5), 535–542. https://doi.org/10.1080/0144619032000073523

Ammar, M. A. (2013). LOB and CPM integrated method for scheduling repetitive projects. Journal of Construction Engineering and Management, 139(1), 44–50. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000569

Ammar, M. A. (2020). Resource optimisation in line of balance scheduling. Construction Management and Economics, 38(8), 715–725. https://doi.org/10.1080/01446193.2019.1606924

Ammar, M. A. (2022). Optimization of line of balance scheduling considering work interruption. International Journal of Construction Management, 22(2), 305–316. https://doi.org/10.1080/15623599.2019.1624003

Ammar, M. A., & Abdel-Maged, A. F. (2018). Modeling of LOB scheduling with learning development effect. International Journal of Construction Management, 18(6), 517–526. https://doi.org/10.1080/15623599.2017.1357350

Arabpour Roghabadi, M., & Moselhi, O. (2021). Optimized crew selection for scheduling of repetitive projects. Engineering, Construction and Architectural Management, 28(6), 1517–1540. https://doi.org/10.1108/ECAM-10-2019-0590

Arditi, D., & Albulak, M. Z. (1986). Line-of-Balance scheduling in pavement construction. Journal of Construction Engineering and Management, 112(3), 411–424. https://doi.org/10.1061/(ASCE)0733-9364(1986)112:3(411)

Arditi, D., Tokdemir, O. B., & Suh, K. (2001). Scheduling system for repetitive unit construction using line-of-balance technology. Engineering, Construction and Architectural Management, 8(2), 90–103. https://doi.org/10.1108/eb021173

Arditi, D., Tokdemir, O. B., & Suh, K. (2002a). Challenges in line-of-balance scheduling. Journal of Construction Engineering and Management, 128(6), 545–556. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:6(545)

Arditi, D., Sikangwan, P., & Tokdemir, O. B. (2002b). Scheduling system for high rise building construction. Construction Management and Economics, 20(4), 353–364. https://doi.org/10.1080/01446190210131647

Bakry, I., Moselhi, O., & Zayed, T. (2014). Optimized acceleration of repetitive construction projects. Automation in Construction, 39, 145–151. https://doi.org/10.1016/j.autcon.2013.07.003

Bakry, I., Moselhi, O., & Zayed, T. (2016). Optimized scheduling and buffering of repetitive construction projects under uncertainty. Engineering, Construction and Architectural Management, 23(6), 782–800. https://doi.org/10.1108/ECAM-05-2014-0069

Baqerin, M. H., Shafahi, Y., & Kashani, H. (2016). Application of Weibull analysis to evaluate and forecast schedule performance in repetitive projects. Journal of Construction Engineering and Management, 142(2), 04015058. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001040

Biruk, S., & Jaśkowski, P. (2008). Simulation modelling construction project with repetitive tasks using Petri nets theory. Journal of Business Economics and Management, 9(3), 219–226. https://doi.org/10.3846/1611-1699.2008.9.219-226

Biruk, S., & Jaśkowski, P. (2009). The work continuity constraints problem in construction projects, network models. Archives of Civil Engineering, 55(1), 29–41.

Biruk, S., & Rzepecki, Ł. (2017). Wpływ zjawiska uczenia siȩ i zapominania na czas realizacji powtarzalnych procesów budowlanych realizowanych w warunkach losowyc [The impact of learning-forgetting phenomenon on duration of repetitive construction processes conducted in random conditions]. Scientific Review Engineering and Environmental Sciences, 26(2), 202–209. https://doi.org/10.22630/PNIKS.2017.26.2.18

Bonnal, P., Gourc, D., Hameri, A.-P., & Lacoste, G. (2005). A linear-discrete scheduling model for the resource-constrained project scheduling problem. Construction Management and Economics, 23(8), 797–814. https://doi.org/10.1080/01446190500040869

Bonnal, P., Baudin, M., & De Jonghe, J. (2013). Merging PDM, RSM and LSM scheduling approaches: Into a single construction project scheduling system. Journal of Modern Project Management, 1(2), 6–17.

Bożejko, W., Hejducki, Z., & Wodecki, M. (2012). Applying metaheuristic strategies in construction projects management. Journal of Civil Engineering and Management, 18(5), 621–630. https://doi.org/10.3846/13923730.2012.719837

Bożejko, W., Hejducki, Z., Uchroński, M., & Wodecki, M. (2014). Solving resource-constrained construction scheduling problems with overlaps by metaheuristic. Journal of Civil Engineering and Management, 20(5), 649–659. https://doi.org/10.3846/13923730.2014.906496

Cheng, T.-M., Feng, C.-W., & Chen, Y.-L. (2005). A hybrid mechanism for optimizing construction simulation models. Automation in Construction, 14(1), 85–98. https://doi.org/10.1016/j.autcon.2004.07.014

Cho, K., Hong, T., & Hyun, C. (2010). Integrated schedule and cost model for repetitive construction process. Journal of Management in Engineering, 26(2), 78–88. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000009

Cho, K., Hong, T., & Hyun, C. (2011). Scheduling model for repetitive construction processes for high-rise buildings. Canadian Journal of Civil Engineering, 38(1), 36–48. https://doi.org/10.1139/L10-108

Cho, K., Hong, T., & Hyun, C. (2013). Space zoning concept-based scheduling model for repetitive construction process. Journal of Civil Engineering and Management, 19(3), 409–421. https://doi.org/10.3846/13923730.2012.757561

Chrzanowski, E. N., & Johnston, D. W. (1986). Application of linear scheduling. Journal of Construction Engineering and Management, 112(4), 476–491. https://doi.org/10.1061/(ASCE)0733-9364(1986)112:4(476)

Cole, L. J. R. (1991). Construction scheduling: Principles, practices, and six case studies. Journal of Construction Engineering and Management, 117(4), 579–588. https://doi.org/10.1061/(ASCE)0733-9364(1991)117:4(579)

Couto, J. P., & Teixeira, J. C. (2005). Using linear model for learning curve effect on highrise floor construction. Construction Management and Economics, 23(4), 355–364. https://doi.org/10.1080/01446190500040505

Damci, A. (2020). Revisiting the concept of natural rhythm of production in line of balance scheduling. International Journal of Construction Management. https://doi.org/10.1080/15623599.2020.1786764

Damci, A., Arditi, D., & Polat, G. (2013a). Multiresource leveling in line-of-balance scheduling. Journal of Construction Engineering and Management, 139(9), 1108–1116. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000716

Damci, A., Arditi, D., & Polat, G. (2013b). Resource leveling in line-of-balance scheduling. Computer-Aided Civil and Infrastructure Engineering, 28(9), 679–692. https://doi.org/10.1111/mice.12038

de Araújo, M. C. B., Alencar, L. H., & de Miranda Mota, C. M. (2017). Project procurement management: A structured literature review. International Journal of Project Management, 35(3), 353–377. https://doi.org/10.1016/j.ijproman.2017.01.008

Dhanasekar, M. (2000). Identification of optimal size resources for a repetitive housing construction. Engineering, Construction and Architectural Management, 7(4), 347–361. https://doi.org/10.1108/eb021158

Duffy, G. A., Oberlender, G. D., & Jeong, D. H. S. (2011). Linear scheduling model with varying production rates. Journal of Construction Engineering and Management, 137(8), 574–582. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000320

Duffy, G., Woldesenbet, A., Jeong, D. H. S., & Oberlender, G. D.

(2012). Advanced linear scheduling program with varying production rates for pipeline construction projects. Automation in Construction, 27, 99–110. https://doi.org/10.1016/j.autcon.2012.05.014

Dzeng, R. J., Wang, W. C., & Tserng, H. P. (2004). Module-based construction schedule administration for public infrastructure agencies. Journal of Construction Engineering and Management, 130(1), 5–14. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:1(5)

Eid, M. S., Elbeltagi, E. E., & El-Adaway, I. H. (2021). Simultaneous multi-criteria optimization for scheduling linear infrastructure projects. International Journal of Construction Management, 21(1), 41–55. https://doi.org/10.1080/15623599.2018.1505027

Eiris Pereira, R., & Flood, I. (2017). Impact of linear correlation on construction project performance using stochastic linear scheduling. Visualization in Engineering, 5, 8. https://doi.org/10.1186/s40327-017-0045-2

El-Rayes, K. (2001). Object-oriented model for repetitive construction scheduling. Journal of Construction Engineering and Management, 127(3), 199–205. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:3(199)

El-Rayes, K., & Moselhi, O. (1998). Resource-driven scheduling of repetitive activities. Construction Management and Economics, 16(4), 433–446. https://doi.org/10.1080/014461998372213

El-Rayes, K., & Moselhi, O. (2001). Optimizing resource utilization for repetitive construction projects. Journal of Construction Engineering and Management, 127(1), 18–26. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:1(18)

El-Rayes, K., Ramanathan, R., & Moselhi, O. (2002). An object-oriented model for planning and control of housing construction. Construction Management and Economics, 20(3), 201–210. https://doi.org/10.1080/01446190110115312

Elhakeem, A., & Hegazy, T. (2005). Graphical approach for manpower planning in infrastructure networks. Journal of Construction Engineering and Management, 131(2), 168–175. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:2(168)

Ezeldin, A. S., & Soliman, A. (2009). Hybrid time-cost optimization of nonserial repetitive construction projects. Journal of Construction Engineering and Management, 135(1), 42–55. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:1(42)

Fan, S.-L., & Tserng, H. P. (2006). Object-oriented scheduling for repetitive projects with soft logics. Journal of Construction Engineering and Management, 132(1), 35–48. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:1(35)

Fan, S.-L., Sun, K.-S., & Wang, Y.-R. (2012). GA optimization model for repetitive projects with soft logic. Automation in Construction, 21(1), 253–261. https://doi.org/10.1016/j.autcon.2011.06.009

García-Nieves, J. D. D., Ponz-Tienda, J. L. L., Salcedo-Bernal, A., & Pellicer, E. (2018). The multimode resource-constrained project scheduling problem for repetitive activities in construction projects. Computer-Aided Civil and Infrastructure Engineering, 33(8), 655–671. https://doi.org/10.1111/mice.12356

García-Nieves, J. D. D., Ponz-Tienda, J. L. L., Ospina-Alvarado, A., & Bonilla-Palacios, M. (2019). Multipurpose linear programming optimization model for repetitive activities scheduling in construction projects. Automation in Construction, 105, 102799. https://doi.org/10.1016/j.autcon.2019.03.020

Georgy, M. E. (2008). Evolutionary resource scheduler for linear projects. Automation in Construction, 17(5), 573–583. https://doi.org/10.1016/j.autcon.2007.10.005

González, V., Alarcón, L. F., & Molenaar, K. (2009). Multiobjective design of Work-In-Process buffer for scheduling repetitive building projects. Automation in Construction, 18(2), 95–108. https://doi.org/10.1016/j.autcon.2008.05.005

Gouda, A., Hosny, O., & Nassar, K. (2017). Optimal crew routing for linear repetitive projects using graph theory. Automation in Construction, 81, 411–421. https://doi.org/10.1016/j.autcon.2017.03.007

Hafez, S. M. (2004). Practical limitations of line-of-balance in scheduling repetitive construction units. Alexandria Engineering Journal, 43(5), 653–661.

Hafez, S. M. (2005). Developing classical schedule technology. Alexandria Engineering Journal, 44(2), 267–277.

Hajdasz, M. (2014). Flexible management of repetitive construction processes by an intelligent support system. Expert Systems with Applications, 41(4, Part 1), 962–973. https://doi.org/10.1016/j.eswa.2013.06.063

Han, S., Lee, S., & Peña-Mora, F. (2012). Identification and quantification of non-value-adding effort from errors and changes in design and construction projects. Journal of Construction Engineering and Management, 138(1), 98–109. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000406

Handa, V. K., & Barcia, R. M. (1986). Linear scheduling using optimal control theory. Journal of Construction Engineering and Management, 112(3), 387–393. https://doi.org/10.1061/(asce)0733-9364(1986)112:3(387)

Harmelink, D. J. (2001). Linear scheduling model: Float characteristics. Journal of Construction Engineering and Management, 127(4), 255–260. https://doi.org/10.1061/(asce)0733-9364(2001)127:4(255)

Harmelink, D. J., & Rowings, J. E. (1998). Linear scheduling model: Development of controlling activity path. Journal of Construction Engineering and Management, 124(4), 263–268. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:4(263)

Harris, R. B., & Ioannou, P. G. (1998). Scheduling projects with repeating activities. Journal of Construction Engineering and Management, 124(4), 269–278. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:4(269)

Hassan, A., & El-Rayes, K. (2020). Quantifying the interruption impact of activity delays in non-serial repetitive construction projects. Construction Management and Economics, 38(6), 515–533. https://doi.org/10.1080/01446193.2019.1657922

Hassan, A., El-Rayes, K., & Attalla, M. (2021). Optimizing the scheduling of crew deployments in repetitive construction projects under uncertainty. Engineering, Construction and Architectural Management, 28(6), 1615–1634. https://doi.org/10.1108/ECAM-05-2020-0304

Hassanein, A., & Moselhi, O. (2004). Planning and scheduling highway construction. Journal of Construction Engineering and Management, 130(5), 638–646. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:5(638)

Hassanein, A., & Moselhi, O. (2005). Accelerating linear projects. Construction Management and Economics, 23(4), 377–385. https://doi.org/10.1080/01446190410001673571

Hegazy, T. (2001). Critical path method-line of balance model for efficient scheduling of repetitive construction projects. Transportation Research Record: Journal of the Transportation Research Board, 1761(1), 124–129. https://doi.org/10.3141/1761-16

Hegazy, T., & Wassef, N. (2001). Cost optimization in projects with repetitive nonserial activities. Journal of Construction Engineering and Management, 127(3), 183–191. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:3(183)

Hegazy, T., & Kamarah, E. (2008). Efficient repetitive scheduling for high-rise construction. Journal of Construction Engineering and Management, 134(4), 253–264. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:4(253)

Hegazy, T., Elhakeem, A., & Elbeltagi, E. (2004). Distributed scheduling model for infrastructure networks. Journal of Construction Engineering and Management, 130(2), 160–167. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:2(160)

Hegazy, T., Abdel-Monem, M., & Atef Saad, D. (2014). Framework for enhanced progress tracking and control of linear projects. Engineering, Construction and Architectural Management, 21(1), 94–110. https://doi.org/10.1108/ECAM-08-2012-0080

Hegazy, T., Atef Saad, D., & Mostafa, K. (2020). Enhanced repetitive-scheduling computation and visualization. Journal of Construction Engineering and Management, 146(10), 04020118. https://doi.org/10.1061/(asce)co.1943-7862.0001911

Hejducki, Z. (2003). Scheduling model of construction activity with time couplings. Journal of Civil Engineering and Management, 9(4), 284–291. https://doi.org/10.1080/13923730.2003.10531341

Heravi, G., & Moridi, S. (2019). Resource-constrained time-cost tradeoff for repetitive construction projects. KSCE Journal of Civil Engineering, 23(8), 3265–3274. https://doi.org/10.1007/s12205-019-0151-x

Hsie, M., Chang, C.-J., Yang, I.-T., & Huang, C.-Y. (2009). Resource-constrained scheduling for continuous repetitive projects with time-based production units. Automation in Construction, 18(7), 942–949. https://doi.org/10.1016/j.autcon.2009.04.006

Hu, D., & Mohamed, Y. (2014). Simulation-model-structuring methodology for industrial construction fabrication shops. Journal of Construction Engineering and Management, 140(5), 04014002. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000825

Huang, Y.-C. (2006). Graphical-based multistage scheduling method for RC buildings. Construction Management and Economics, 24(1), 5–18. https://doi.org/10.1080/01446190500183743

Huang, R.-Y., & Halpin, D. W. (2000). Graphically based LP modelling for linear scheduling analysis: The POLO system. Engineering, Construction and Architectural Management, 7(1), 41–51. https://doi.org/10.1108/eb021131

Huang, R.-Y., & Sun, K.-S. (2005). System development for non-unit based repetitive project scheduling. Automation in Construction, 14(5), 650–665. https://doi.org/10.1016/j.autcon.2005.02.003

Huang, R.-Y., & Sun, K.-S. (2006a). An optimization model for workgroup-based repetitive scheduling. Canadian Journal of Civil Engineering, 33(9), 1172–1194. https://doi.org/10.1139/l06-057

Huang, R.-Y., & Sun, K.-S. (2006b). Non-unit-based planning and scheduling of repetitive construction projects. Journal of Construction Engineering and Management, 132(6), 585–597. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:6(585)

Huang, R.-Y., & Sun, K.-S. (2009). A GA optimization model for workgroup-based repetitive scheduling (WoRSM). Advances in Engineering Software, 40(3), 212–228. https://doi.org/10.1016/j.advengsoft.2008.01.010

Huang, Y., Zou, X., & Zhang, L. (2016). Genetic algorithm-based method for the deadline problem in repetitive construction projects considering soft logic. Journal of Management in Engineering, 32(4), 04016002. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000426

Hyari, K. H., & El-Rayes, K. (2006). Optimal planning and scheduling for repetitive construction projects. Journal of Management in Engineering, 22(1), 11–19. https://doi.org/10.1061/(ASCE)0742-597X(2006)22:1(11)

Hyari, K. H., El-Rayes, K., & El-Mashaleh, M. (2009). Automated trade-off between time and cost in planning repetitive construction projects. Construction Management and Economics, 27(8), 749–761. https://doi.org/10.1080/01446190903117793

Hyun, H., Jung, M., Yoon, I., Lee, H. S., & Lee, J. (2021). Multiple work zone strategy for repetitive on-site work of modular construction using parallel station method. Journal of Asian Architecture and Building Engineering, 20(3), 285–297. https://doi.org/10.1080/13467581.2020.1782917

Ioannou, P. G., & Yang, I.-T. (2016). Repetitive scheduling method: Requirements, modeling, and implementation. Journal of Construction Engineering and Management, 142(5), 04016002. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001107

Ipsilandis, P. G. (2007). Multiobjective linear programming model for scheduling linear repetitive projects. Journal of Construction Engineering and Management, 133(6), 417–424. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:6(417)

Jaafari, A. (1984). Criticism of CPM for project planning analysis. Journal of Construction Engineering and Management, 110(2), 222–233. https://doi.org/10.1061/(ASCE)0733-9364(1984)110:2(222)

Jaśkowski, P., & Biruk, S. (2018). Reducing renewable resource demand fluctuation using soft precedence relations in project scheduling. Journal of Civil Engineering and Management, 24(4), 355–363. https://doi.org/10.3846/jcem.2018.3043

Jaśkowski, P., & Biruk, S. (2019). Minimizing the duration of repetitive construction processes with work continuity constraints. Computation, 7(1), 14. https://doi.org/10.3390/computation7010014

Jordan Srour, F., Kiomjian, D., & Srour, I. M. (2018). Automating the use of learning curve models in construction task duration estimates. Journal of Construction Engineering and Management, 144(7), 04018055. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001515

Kallantzis, A., Soldatos, J., & Lambropoulos, S. (2007). Linear versus network scheduling: A critical path comparison. Journal of Construction Engineering and Management, 133(7), 483–491. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:7(483)

Kang, L. S., Park, I. C., & Lee, B. H. (2001). Optimal schedule planning for multiple, repetitive construction process. Journal of Construction Engineering and Management, 127(5), 382–390. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:5(382)

Katsuragawa, C. M., Lucko, G., Isaac, S., & Su, Y. (2021). Fuzzy linear and repetitive scheduling for construction projects. Journal of Construction Engineering and Management, 147(3), 04021002. https://doi.org/10.1061/(asce)co.1943-7862.0001996

Kavanagh, D. P. (1985). Siren: A repetitive construction simulation model. Journal of Construction Engineering and Management, 111(3), 308–323. https://doi.org/10.1061/(ASCE)0733-9364(1985)111:3(308)

Lam, K. C., Lee, D., & Hu, T. (2001). Understanding the effect of the learning-forgetting phenomenon to duration of projects construction. International Journal of Project Management, 19(7), 411–420. https://doi.org/10.1016/S0263-7863(00)00025-9

Lee, J.-S. (2016). Estimating cumulative damages due to disruptions in repetitive construction. Journal of Construction Engineering and Management, 142(11), 1–11. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001184

Lee, H.-S., Roh, S., Park, M.-S., & Ryu, H.-G. (2010). Optimal option selection for finishing works of high-rise building. KSCE Journal of Civil Engineering, 14(5), 639–651. https://doi.org/10.1007/s12205-010-0904-z

Lee, D., Kim, D.-S., Kim, G.-H., & Kim, S. (2016). Time reduction effect of the enhanced TACT method for high-rise residential buildings. Journal of Civil Engineering and Management, 22(7), 944–953. https://doi.org/10.3846/13923730.2014.945949

Lee, S., Lee, S., & Son, J. (2016). Developing a process model for optimizing linear process plans based on three types of buffers and brute-force algorithm. Journal of Asian Architecture and Building Engineering, 15(2), 215–222. https://doi.org/10.3130/jaabe.15.215

Leu, S. S., & Hwang, S. T. (2001). Optimal repetitive scheduling model with shareable resource constraint. Journal of Construction Engineering and Management, 127(4), 270–280. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:4(270)

Liu, S. S., & Wang, C. J. (2007). Optimization model for resource assignment problems of linear construction projects. Automation in Construction, 16(4), 460–473. https://doi.org/10.1016/j.autcon.2006.08.004

Liu, S. S., & Wang, C. J. (2009). Two-stage profit optimization model for linear scheduling problems considering cash flow. Construction Management and Economics, 27(11), 1023–1037. https://doi.org/10.1080/01446190903233111

Liu, S. S., & Wang, C. J. (2012). Optimizing linear project scheduling with multi-skilled crews. Automation in Construction, 24, 16–23. https://doi.org/10.1016/j.autcon.2011.12.009

Long, L. D., & Ohsato, A. (2009). A genetic algorithm-based method for scheduling repetitive construction projects. Automation in Construction, 18(4), 499–511. https://doi.org/10.1016/j.autcon.2008.11.005

Lu, M., & Li, H. (2003). Resource-activity critical-path method for construction planning. Journal of Construction Engineering and Management, 129(4), 412–420. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:4(412)

Lucko, G. (2008). Productivity scheduling method compared to linear and repetitive project scheduling methods. Journal of Construction Engineering and Management, 134(9), 711–720. https://doi.org/10.1061/(asce)0733-9364(2008)134:9(711)

Lucko, G. (2009). Productivity scheduling method: Linear schedule analysis with singularity functions. Journal of Construction Engineering and Management, 135(4), 246–253. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:4(246)

Lucko, G. (2011a). Integrating efficient resource optimization and linear schedule analysis with singularity functions. Journal of Construction Engineering and Management, 137(1), 45–55. https://doi.org/10.1061/(asce)co.1943-7862.0000244

Lucko, G. (2011b). Optimizing cash flows for linear schedules modeled with singularity functions by simulated annealing. Journal of Construction Engineering and Management, 137(7), 523–535. https://doi.org/10.1061/(asce)co.1943-7862.0000324

Lucko, G., & Peña Orozco, A. A. (2009). Float types in linear schedule analysis with singularity functions. Journal of Construction Engineering and Management, 135(5), 368–377. https://doi.org/10.1061/(asce)co.1943-7862.0000007

Lucko, G., & Gattei, G. (2016). Line-of-balance against linear scheduling: Critical comparison. Proceedings of Institution of Civil Engineers: Management, Procurement and Law, 169(1), 26–44. https://doi.org/10.1680/jmapl.15.00016

Lucko, G., Alves, T. D. C. L., & Angelim, V. L. (2014a). Challenges and opportunities for productivity improvement studies in linear, repetitive, and location-based scheduling. Construction Management and Economics, 32(6), 575–594. https://doi.org/10.1080/01446193.2013.845305

Lucko, G., Said, H. M. M., & Bouferguene, A. (2014b). Construction spatial modeling and scheduling with three-dimensional singularity functions. Automation in Construction, 43, 132–143. https://doi.org/10.1016/j.autcon.2014.03.008

Lucko, G., Araújo, L. G., & Cates, G. R. (2016). Slip chart-inspired project schedule diagramming: origins, buffers, and extension to linear schedules. Journal of Construction Engineering and Management, 142(5), 04015101. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001089

Lutz, J. D., & Hijazi, A. (1993). Planning repetitive construction: Current practice. Construction Management and Economics, 11(2), 99–110. https://doi.org/10.1080/01446199300000003

Mahdi, I. M. (2004). A new LSM approach for planning repetitive housing projects. International Journal of Project Management, 22(4), 339–346. https://doi.org/10.1016/S0263-7863(03)00071-1

Maravas, A., & Pantouvakis, J.-P. (2011). Fuzzy repetitive scheduling method for projects with repeating activities. Journal of Construction Engineering and Management, 137(7), 561–564. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000319

Mattila, K. G., & Abraham, D. M. (1998). Resource leveling of linear schedules using integer linear programming. Journal of Construction Engineering and Management, 124(3), 232–244. https://doi.org/10.1061/(asce)0733-9364(1998)124:3(232)

Mattila, K. G., & Park, A. (2003). Comparison of linear scheduling model and repetitive scheduling method. Journal of Construction Engineering and Management, 129(1), 56–64. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:1(56)

Moreno, F., Orozco, F., Rojas, O., Senior, B. A., Poshdar, M., & Forcael, E. (2020). A fixed start scheduling approach for repetitive construction projects. KSCE Journal of Civil Engineering, 24, 1671–1682. https://doi.org/10.1007/s12205-020-1429-8

Moselhi, O., & El-Rayes, K. (1993a). Least cost scheduling for repetitive projects. Canadian Journal of Civil Engineering, 20(5), 834–843. https://doi.org/10.1139/l93-109

Moselhi, O., & El-Rayes, K. (1993b). Scheduling of repetitive projects with cost optimization. Journal of Construction Engineering and Management, 119(4), 681–697. https://doi.org/10.1061/(ASCE)0733-9364(1993)119:4(681)

Moselhi, O., & Hassanein, A. (2003). Optimized scheduling of linear projects. Journal of Construction Engineering and Management, 129(6), 664–673. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:6(664)

Moselhi, O., Bakry, I., & Alshibani, A. (2016). Accelerating repetitive construction projects: With uncertainty and contractors’ judgment. Canadian Journal of Civil Engineering, 43(11), 949–957. https://doi.org/10.1139/cjce-2014-0347

Murguia, D., & Urbina, A. (2018). Complex production systems: Non-linear and non-repetitive projects. In 26th Annual Conference of the International Group for Lean Construction (pp. 858–868), Chennai, India. https://doi.org/10.24928/2018/0222

Naresh, A. L., & Jahren, C. T. (1999). Learning outcomes from construction simulation modeling. Journal of Civil Engineering and Environmental Systems, 16(2), 129–144. https://doi.org/10.1080/02630259908970257

Nassar, K. (2005). Evolutionary optimization of resource allocation in repetitive construction schedules. Electronic Journal of Information Technology in Construction (ITcon), 10, 265–273.

O’Brien, J. J., Kreitzberg, F. C., & Mikes, W. F. (1985). Network scheduling variations for repetitive work. Journal of Construction Engineering and Management, 111(2), 105–116. https://doi.org/10.1061/(ASCE)0733-9364(1985)111:2(105)

Podolski, M. (2017). Management of resources in multiunit construction projects with the use of a tabu search algorithm. Journal of Civil Engineering and Management, 23(2), 263–272. https://doi.org/10.3846/13923730.2015.1073616

Podolski, M., & Sroka, B. (2019). Cost optimization of multiunit construction projects using linear programming and metaheuristic-based simulated annealing algorithm. Journal of Civil Engineering and Management, 25(8), 848–857. https://doi.org/10.3846/jcem.2019.11308

Radziszewska-Zielina, E., & Sroka, B. (2018). Planning repetitive construction projects considering technological constraints. Open Engineering, 8(1), 500–505. https://doi.org/10.1515/eng-2018-0058

Reda, R. M. (1990). RPM: Repetitive Project Modeling. Journal of Construction Engineering and Management, 116(2), 316–330. https://doi.org/10.1061/(ASCE)0733-9364(1990)116:2(316)

Rogalska, M., & Hejducki, Z. (2007). Time buffers in construction process scheduling. Journal of Civil Engineering and Management, 13(2), 143–148. https://doi.org/10.1080/13923730.2007.9636430

Rogalska, M., Bożejko, W., & Hejducki, Z. (2008). Time/cost optimization using hybrid evolutionary algorithm in construction project scheduling. Automation in Construction, 18(1), 24–31. https://doi.org/10.1016/j.autcon.2008.04.002

Roofigari-Esfahan, N., & Razavi, S. (2017). Uncertainty-aware linear schedule optimization: A space-time constraint-satisfaction approach. Journal of Construction Engineering and Management, 143(5), 04016132. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001276

Russell, A. D. (1985). Microcomputers, management, and high-rise construction: The next step. Canadian Journal of Civil Engineering, 12(2), 396–414. https://doi.org/10.1139/l85-042

Russell, A. D., & Caselton, W. F. (1988). Extensions to linear scheduling optimization. Journal of Construction Engineering and Management, 114(1), 36–52. https://doi.org/10.1061/(ASCE)0733-9364(1988)114:1(36)

Russell, A. D., & Wong, W. C. M. (1993). New generation of planning structures. Journal of Construction Engineering and Management, 119(2), 196–214. https://doi.org/10.1061/(ASCE)0733-9364(1993)119:2(196)

Russell, A., Staub-French, S., Tran, N., & Wong, W. (2009). Visualizing high-rise building construction strategies using linear scheduling and 4D CAD. Automation in Construction, 18(2), 219–236. https://doi.org/10.1016/j.autcon.2008.08.001

Salama, T., & Moselhi, O. (2019). Multi-objective optimization for repetitive scheduling under uncertainty. Engineering, Construction and Architectural Management, 26(7), 1294–1320. https://doi.org/10.1108/ECAM-05-2018-0217

Salama, T., Salah, A., & Moselhi, O. (2018). Integration of linear scheduling method and the critical chain project management. Canadian Journal of Civil Engineering, 45(1), 30–40. https://doi.org/10.1139/cjce-2017-0020

Sarraj, Z. M. A. (1990). Formal development of line-of-balance technique. Journal of Construction Engineering and Management, 116(4), 689–704. https://doi.org/10.1061/(ASCE)0733-9364(1990)116:4(689)

Sawhney, A., Mund, A., & Chaitavatputtiporn, T. (2003). Petri Net-based scheduling of construction projects. Civil Engineering and Environmental Systems, 20(4), 255–271. https://doi.org/10.1080/10286600310001633848

Senior, B. A., & Halpin, D. W. (1998). Simplified simulation system for construction projects. Journal of Construction Engineering and Management, 124(1), 72–81. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:1(72)

Seuring, S., & Müller, M. (2008). From a literature review to a conceptual framework for sustainable supply chain management. Journal of Cleaner Production, 16(15), 1699–1710. https://doi.org/10.1016/j.jclepro.2008.04.020

Sharma, S., & Bansal, V. K. (2018). Location-based planning and scheduling of highway construction projects in hilly terrain using GIS. Canadian Journal of Civil Engineering, 45(7), 570–582. https://doi.org/10.1139/cjce-2017-0359

Sharma, H., McIntyre, C., Gao, Z., & Nguyen, T.-H. (2009). Developing a traffic closure integrated linear schedule for highway rehabilitation projects. Journal of Construction Engineering and Management, 135(3), 146–155. https://doi.org/10.1061/(asce)0733-9364(2009)135:3(146)

Shim, E., & Kim, B.-C. (2014). Batch-size based repetitive scheduling method (BRSM). International Journal of Construction Education and Research, 10(2), 140–156. https://doi.org/10.1080/15578771.2013.826753

Shtub, A., LeBlanc, L. J., & Cai, Z. (1996). Scheduling programs with repetitive projects: A comparison of a simulated annealing, a genetic and a pair-wise swap algorithm. European Journal of Operational Research, 88(1), 124–138. https://doi.org/10.1016/0377-2217(94)00158-8

Su, Y., & Lucko, G. (2016). Linear scheduling with multiple crews based on line-of-balance and productivity scheduling method with singularity functions. Automation in Construction, 70, 38–50. https://doi.org/10.1016/j.autcon.2016.05.011

Suhail, S. A., & Neale, R. H. (1994). CPM/LOB: New methodology to integrate CPM and line of balance. Journal of Construction Engineering and Management, 120(3), 667–684. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:3(667)

Suresh, M., Dutta, P., & Jain, K. (2011). Analysis of an EPC project: A solution to the resource constrained project scheduling problem using genetic algorithms. International Journal of Industrial and Systems Engineering, 8(2), 251–269. https://doi.org/10.1504/IJISE.2011.041372

Tang, Y., Liu, R., & Sun, Q. (2014a). Schedule control model for linear projects based on linear scheduling method and constraint programming. Automation in Construction, 37, 22–37. https://doi.org/10.1016/j.autcon.2013.09.008

Tang, Y., Liu, R., & Sun, Q. (2014b). Two-stage scheduling model for resource leveling of linear projects. Journal of Construction Engineering and Management, 140(7), 04014022. https://doi.org/10.1061/(asce)co.1943-7862.0000862

Tang, Y., Sun, Q., Liu, R., & Wang, F. (2018). Resource leveling based on line of balance and constraint programming. Computer-Aided Civil and Infrastructure Engineering, 33(10), 864–884. https://doi.org/10.1111/mice.12383

Tao, S., Wu, C., Sheng, Z., & Wang, X. (2018). Space-time repetitive project scheduling considering location and congestion. Journal of Computing in Civil Engineering, 32(3), 04018017. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000745

Thabet, W. Y., & Beliveau, Y. J. (1994a). Modeling work space to schedule repetitive floors in multistory buildings. Journal of Construction Engineering and Management, 120(1), 96–116. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:1(96)

Thabet, W. Y., & Beliveau, Y. J. (1994b). HVLS: Horizontal and vertical logic scheduling for multistory projects. Journal of Construction Engineering and Management, 120(4), 875–892. https://doi.org/10.1061/(ASCE)0733-9364(1994)120:4(875)

Thabet, W. Y., & Beliveau, Y. J. (1997). SCaRC: Space-Constrained Resource-Constrained scheduling system. Journal of Computing in Civil Engineering, 11(1), 48–59. https://doi.org/10.1061/(ASCE)0887-3801(1997)11:1(48)

Tokdemir, O. B., Arditi, D., & Balcik, C. (2006). ALISS: Advanced Linear Scheduling System. Construction Management and Economics, 24(12), 1253–1267. https://doi.org/10.1080/01446190600953706

Tokdemir, O. B., Erol, H., & Dikmen, I. (2019). Delay risk assessment of repetitive construction projects using line-of-balance scheduling and Monte Carlo simulation. Journal of Construction Engineering and Management, 145(2), 04018132. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001595

Tomar, A., & Bansal, V. K. (2019). Scheduling of repetitive construction projects using geographic information systems: an integration of critical path method and line of balance. Asian Journal of Civil Engineering, 20(4), 549–562. https://doi.org/10.1007/s42107-019-00123-3

Tomar, A., & Bansal, V. K. (2020). A Novel Step Toward Repetitive Projects Scheduling Using Geographic Information Systems. Arabian Journal for Science and Engineering, 45(5), 3983–3997. https://doi.org/10.1007/s13369-019-04330-7

Tomar, A., & Bansal, V. K. (2022). Generation, visualization, and evaluation schedule of repetitive construction projects using GIS. International Journal of Construction Management, 22(6), 1104–1119. https://doi.org/10.1080/15623599.2019.1683691

Tomczak, M. (2019). Modeling of the harmonization method for executing a multi-unit construction project. Open Engineering, 9(1), 282–291. https://doi.org/10.1515/eng-2019-0036

Tomczak, M., & Jaśkowski, P. (2020). New approach to improve general contractor crew’s work continuity in repetitive construction projects. Journal of Construction Engineering and Management, 146(5), 04020043. https://doi.org/10.1061/(asce)co.1943-7862.0001824

Tomczak, M., & Jaśkowski, P. (2021). Preferences of construction managers regarding the quality and optimization criteria of project schedules. Sustainability, 13(2), 544. https://doi.org/10.3390/su13020544

Tran, D.-H., Luong, D.-L., Duong, M.-T., Le, T.-N., & Pham, A.-D. (2018). Opposition multiple objective symbiotic organisms search (OMOSOS) for time, cost, quality and work continuity tradeoff in repetitive projects. Journal of Computational Design and Engineering, 5(2), 160–172. https://doi.org/10.1016/j.jcde.2017.11.008

Tran, D.-H., Chou, J.-S., & Luong, D.-L. (2019). Multi-objective symbiotic organisms optimization for making time-cost tradeoffs in repetitive project scheduling problem. Journal of Civil Engineering and Management, 25(4), 322–339. https://doi.org/10.3846/jcem.2019.9681

Tran, D.-H., Chou, J.-S., & Luong, D.-L. (2020). Optimizing non-unit repetitive project resource and scheduling by evolutionary algorithms. Operational Research, 22, 77–103. https://doi.org/10.1007/s12351-019-00544-7

Ungureanu, L. C., Hartmann, T., & Serbanoiu, I. (2019). Quantitative lean assessment of line of balance schedules’ quality. Engineering, Construction and Architectural Management, 26(2), 224–244. https://doi.org/10.1108/ECAM-05-2017-0088

Vanhoucke, M. (2006). Work continuity constraints in project scheduling. Journal of Construction Engineering and Management, 132(1), 14–25. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:1(14)

Wang, C.-H., & Huang, Y.-C. (1998). Controlling activity interval times in LOB scheduling. Construction Management and Economics, 16(1), 5–16. https://doi.org/10.1080/014461998372547

Wang, T., Abdallah, M., Clevenger, C., & Monghasemi, S. (2021). Time–cost–quality trade-off analysis for planning construction projects. Engineering, Construction and Architectural Management, 28(1), 82–100. https://doi.org/10.1108/ECAM-12-2017-0271

Yamín, R. A., & Harmelink, D. J. (2001). Comparison of Linear Scheduling Model (LSM) and Critical Path Method (CPM). Journal of Construction Engineering and Management, 127(5), 374–381. https://doi.org/10.1061/(asce)0733-9364(2001)127:5(374)

Yang, I.-T., & Ioannou, P. G. (2004). Scheduling system with focus on practical concerns in repetitive projects. Construction Management and Economics, 22(6), 619–630. https://doi.org/10.1080/01446190310001649065

Yang, I.-T., & Chang, C.-Y. (2005). Stochastic resource-constrained scheduling for repetitive construction projects with uncertain supply of resources and funding. International Journal of Project Management, 23(7), 546–553. https://doi.org/10.1016/j.ijproman.2005.03.003

Yi, K. J., Lee, H.-S., & Choi, Y. K. (2002). Network creation and development for repetitive-unit projects. Journal of Construction Engineering and Management, 128(3), 257–264. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:3(257)

Zhang, L., & Qi, J. (2012). Controlling path and controlling segment analysis in repetitive scheduling method. Journal of Construction Engineering and Management, 138(11), 1341–1345. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000535

Zhang, H., Tam, G. M., & Shi, J. J. (2002). Simulation-based methodology for project scheduling. Construction Management and Economics, 20(8), 667–678. https://doi.org/10.1080/0144619022000014088

Zhang, H., Li, H., & Tam, C. M. (2006). Heuristic scheduling of resource-constrained, multiple-mode and repetitive projects. Construction Management and Economics, 24(2), 159–169. https://doi.org/10.1080/01446190500184311

Zhang, L., Zou, X., & Chen, X. (2012). Resource-constrained scheduling in repetitive projects. Advances in Information Sciences and Service Sciences, 4(14), 287–294. https://doi.org/10.4156/aiss.vol4.issue14.35

Zhang, L., Zou, X., & Kan, Z. (2014). Improved strategy for resource allocation in repetitive projects considering the learning effect. Journal of Construction Engineering and Management, 140(11), 04014053. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000896

Zhang, L., Zou, X., & Qi, J. (2015). A trade-off between time and cost in scheduling repetitive construction projects. Journal of Industrial and Management Optimization, 11(4), 1423–1434. https://doi.org/10.3934/jimo.2015.11.1423

Zhang, L., Dai, G., Zou, X., & Qi, J. (2020). Robustness-based multi-objective optimization for repetitive projects under work continuity uncertainty. Engineering, Construction and Architectural Management, 27(10), 3095–3113. https://doi.org/10.1108/ECAM-08-2019-0458

Zolfaghar Dolabi, H. R., Afshar, A., & Abbasnia, R. (2014). CPM/LOB scheduling method for project deadline constraint satisfaction. Automation in Construction, 48, 107–118. https://doi.org/10.1016/j.autcon.2014.09.003

Zou, X., & Zhang, L. (2020). A constraint programming approach for scheduling repetitive projects with atypical activities considering soft logic. Automation in Construction, 109, 102990. https://doi.org/10.1016/j.autcon.2019.102990

Zou, X., Fang, S.-C., Huang, Y.-S., & Zhang, L. (2017). Mixed-integer linear programming approach for scheduling repetitive projects with time-cost trade-off consideration. Journal of Computing in Civil Engineering, 31(3), 06016003. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000641

Zou, X., Wu, G., & Zhang, Q. (2021). Work continuity constraints in repetitive project scheduling considering soft logic. Engineering, Construction and Architectural Management, 28(6), 1713–1738. https://doi.org/10.1108/ECAM-11-2019-0595